Office of Science and Technology and International  
Office of Civilian Radioactive Waste Management
 
Timeline graphic

OCRWM Science and Technology Program
Advanced Welding Technologies

The closure weld and post-weld processing of Alloy 22 waste packages are important to the Yucca Mountain Project (YMP) goal to ensure that these containers will survive their design lifetime in the emplacement environment. There are numerous welding processes that can potentially be used to fabricate these containers and to make the final closure weld.

A scoping study was recently completed which summarized the current “state-of-the-art” of welding process technology in the context of waste package fabrication alternatives. In consideration of the optimum process (or processes) for completing the final closure weld, reliability, efficiency, and long-term performance were weighed more heavily than overall cost of developing or implementing the technology.

Based on the evaluation of a number of candidate processes, friction welding and electron beam welding were identified as potential technologies for the final closure weld. These are both single-pass processes that will allow the final closure weld to be made in minutes rather than the hours required for arc welding processes. Inertia friction welding (IFW) is an extremely robust process that can produce welds of high integrity and low residual stress in Alloy 22. The main disadvantage of this process is that the machine requirements in terms of inertial mass and thrust forces far exceed even the largest of existing IFW machines and the tooling and fixturing required to restrain the waste package during the welding process will require special engineering. The use of IFW represents a technological challenge, but there are no apparent barriers.

Electron beam welding (EBW) will also result in reduced residual stresses and increased process efficiency. Although not as robust as IFW, EBW technology is mature and equipment is commercially available to achieve the weld penetration characteristics required for the closure weld. The evolution of reduced pressure EBW is particularly attractive because it eliminates the need to achieve a vacuum within the welding chamber.

The arc welding processes, gas tungsten arc welding (GTAW) and gas metal arc welding (GMAW), represent lower cost alternatives and are widely used for the fabrication of thick section stainless steels and Ni-base alloys. The main disadvantages with these processes is that total weld time for the closure weld will be extremely long (several hours) and the residual stresses associated with these processes will be high, requiring a post-weld stress relief.

Based on this analysis, the OCRWM Science and Technology Program is preparing a competitive, multiple-award procurement. It is anticipated that bidders will provide proposals for several of these technologies. Initial awards will be to develop proof of principle, followed by a feasibility phase, and a third stage for actual demonstration. Depending on the confidence in successive development activities, the cost and the schedule, further down-selections may be made at each successive phase. A future decision will be made, whether to change the waste package design to incorporate advanced welding technology; any such baseline change will be subject to regulatory review.

 

Office of Science and Technology and International